A Look At The Paraiso District Construction Progress

A Look At The Paraiso District Construction Progress

Earlier this week we showed Gran Paraiso, which is close to topping off and One Paraiso, which will be completed by the end of the year. 

In the Paraiso District, Paraiso Bay is nearly complete and is expected to open soon and topped off in July 2016. 

Both cranes have been removed from Paraiso Bayviews since we last looked in March and the tower topped off in May of this year. 

Construction is also underway on Michael Schwartz's new restaurant at the edge of the water in the Paraiso District called Amara at Paraiso. The restaurant will be 4,500 square feet and have seats for 150. Amara at Paraiso is expected to open in November.

Read More

A Look At The Paraiso Complex - Photos & Video

A Look At The Paraiso Complex - Photos & Video

The 11 acre Paraiso Complex in Edgewater is growing taller as the four buildings - Paraiso Bay, Gran Paraiso, One Paraiso and Paraiso Bayviews continue to top out. 

The 55 story Paraiso Bay topped out in July 2016 and is expected to be completed by this Summer. The 53 story One Paraiso is about to top off and will be completed by the end of the year. Gran Paraiso should top off in the next 3 - 5 months and will be complete by Spring 2018. Gran Paraiso will have 8 bay homes at the base of the building. The last tower, the 44 story Paraiso Bayviews is also close to topping off and will be completed by the end of the year. In total over 1,300 residential units will be delivered to buyers.

Also under construction is the Meyer Davis designed Paraiso Beach Club, which will have a Michael Schwartz Restaurant on the first floor and private residents club on the second floor with a pool. 

Read More

Paraiso Bay And Gran Paraiso Construction Updates

Paraiso Bay And Gran Paraiso Construction Updates

When we last looked at construction on Paraiso Bay, the 55 story condo was about to top off. Since that time, all the windows and balconies are nearly installed with only 4 more floors remaining. 

Construction on Gran Paraiso has reached the 12th floor and has changed significantly since we looked in May. Progress is being made on the amenities deck, which will be shared with residents of Paraiso Bay. Below the amenities deck are the Bay Homes that will have 4 different levels including a rooftop deck with a spa. 

Read More

Paraiso Bay About To Top Off - Plus Construction Photos On All Four Towers

Paraiso Bay About To Top Off - Plus Construction Photos On All Four Towers

The four towers within the 10 acre Paraiso Complex - Paraiso Bay, One Paraiso, Gran Paraiso and Paraiso Bayviews in Edgewater are moving along quickly. 

In March, Paraiso Bay reached the 40th floor and is now currently on the 54th floor of the 55 story building and is about to top out.

Workers are in the process of building the 15th floor of One Paraiso, which was on the 9th floor when we last looked in May. The windows are starting to be installed on the lower portions of the building. 

Paraiso Bayviews is about to hit the 13th floor of construction. Ground breaking on the 44 story tower took place in August 2015.

The last of the four towers in the complex to break ground, Gran Paraiso, is currently on the 6th floor. The building will have 317 residential units and buyers include baseball player Alex Rodriguez and DJ David Guetta.

Just in front of Gran Paraiso is the Paraiso Beach Club, a restaurant by Michael Schwartz which also just started construction.

Read More

Paraiso Construction Updates

Construction at the Paraiso Complex

Construction at the Paraiso Complex

As Paraiso Bay rises taller and is at the 40th floor in the Paraiso complex in Edgewater, the last and final tower - GranParaiso - recently had their groundbreaking.

Paraiso Bayviews is starting to go vertical and is on the 3rd floor of construction.

Previous construction photos can be seen here.

A Look At The Paraiso Construction In Edgewater

The Paraiso Compound in Edgewater

The Paraiso Compound in Edgewater

Construction at the Paraiso development in the Edgewater district of Miami is going quickly. Paraiso Bay is rising taller since we last looked in September 2015, while construction has started on the towers surrounding the building.

Groundbreaking for Paraiso Bayviews started in August 2015, while construction has started on One Paraiso. The final building in the development is Gran Paraiso, which is slated for groundbreaking in the first quarter of 2016.

The Paraiso development is headed by Related Group with Arquitectonica as the architect. Interior design is by Piero Lissoni while Karim Rashid is doing interiors for Paraiso Bayviews. Enzo Enea is doing landscape. The development will also have a Michael Schwartz restaurant on the water called Paraiso Beach Club.

Paraiso Bay Construction Updates

Paraiso Bay

Paraiso Bay in Edgewater is currently on the 19th floor of construction on the 55 story building. Groundbreaking on the site began on July 2014. 

Last month, The Related Group had the groundbreaking of Paraiso Bayviews, which is apart of the Paraiso compound. Photos from the groundbreaking can be seen here.