MDM Group

Avant at Met Square Construction Photos

Avant at Met Square

Avant at Met Square

Construction is progressing at Avant at Met Square since we last looked June and the 43 building just topped off. 

Construction began on the building in August 2015 after being delayed over the discovery of an ancient Tequesta village on the site.

Previous construction photos of Avant at Met Square can be viewed here.

Paramount Miami Worldcenter Construction Updates

Paramount Miami Worldcenter

Paramount Miami Worldcenter

Paramount Miami Worldcenter in Downtown Miami has reached the 27th floor of the 60 story building and close to the halfway mark. A year ago, the tower was just starting to go vertical.

In August, construction had reached the 19th floor and the windows were starting to be installed on the lower floors.

Previous construction photos of Paramount Miami Worldcenter can be viewed here.

Paramount Miami Worldcenter Reaches 19th Floor - Photos & Video

Paramount Miami Worldcenter

Paramount Miami Worldcenter

The 60 story Paramount Miami Worldcenter in Downtown Miami is steadily rising as it reaches the 19th floor after starting to go vertical in November 2016.

Glass is already starting to be installed on the building and the open air mall on the East side of the lot has already started going vertical. 

With 513 residential units, Paramount Miami Worldcenter is expected to be completed in 2018.

Previous construction photos of Paramount Miami Worldcenter can be viewed here.

Avant At Met Square Tops Off

Avant At Met Square Topped Off

The 43 story Avant At Met Square has topped out in Downtown Miami.

Construction began August 2015 and is expected to be completed first quarter 2018.

The windows are almost installed and painting has begun on the exterior of the building.

Previous construction photos of Avant at Met Square can be viewed here.

Avant at Met Square Close To Topping Out

Avant at Met Square

Avant at Met Square

The 43 story Avant at Met Square is close to topping out in Downtown Miami. When we last looked the building just reached the 28th floor. 

Construction started going vertical in January 2016 and the project is expected to be completed by first quarter 2018.

Previous construction photos of Avant at Met Square can be viewed here.

 

Paramount Miami Worldcenter Reaches 9th Floor

Paramount Miami Worldcenter

Paramount Miami Worldcenter

Paramount Miami Worldcenter has reached the 9th floor of construction of the 60 story building since we last looked in April. 

Construction has started on the retail open air mall portion with the vertical columns put in place. 

Miami Worldcenter will also be adding a 24 story hotel with four levels of retail and 200,000 square feet of space.

Paramount Miami Worldcenter Construction Updates

Paramount Miami Worldcenter

Paramount Miami Worldcenter

The 60 story Paramount Miami Worldcenter is continuing to rise since we last looked in February.

Groundbreaking began in March 2016 and started going vertical in November 2016.

Previous construction photos of Paramount Miami Worldcenter can be viewed here.