Coconut Grove

Scotty's Landing Demolished As Construction Continues At Regatta Harbour

Regatta Harbour Coconut Grove Construction

Regatta Harbour Coconut Grove Construction

Since closing a year ago, Scotty’s Landing (Grove Bay Grill) has been demolished to make way for the 7 acre Regatta Harbour. Next to the demolished restaurant was The Chart House restaurant which was also demolished two years ago.

In its place will be a Cut & Dry Restaurant and Afishonado Restaurant, event space, marina with 400 slips, public baywalk and two Pan Am hangars turned into retail space.

The Grove Bay Parking Garage was completed last month and began construction in June 2018.

Previous photos of Regatta Harbour can be viewed here.

Construction Begins at Mr C Residences In Coconut Grove

Mr C Residences Coconut Grove

Mr C Residences Coconut Grove

Construction has started on the 20 story South Tower at Mr C Residences in Coconut Grove located at 2655 South Bayshore Drive, according to The Miami Herald.

The Terra Group developed building will have 118 residences with prices starting at $600,000. The building will include gourmet market, juice bar, Bellini Bar, 24-hour doorman and security, 24-hour valet, pool, Billiards room, library, cinema and business lounge.

Mr. C Residences is located across the street from the under construction Regatta Harbour.

One Park Grove To Open Soon

One Park Grove

One Park Grove

The last tower at the 5.2 acre Park Grove complex, One Park Grove, is almost completed as residents will start to move in soon.

With 64 residential units, One Park Grove was built on the site of the demolished Coconut Grove Bank.

Previous construction photos of One Park Grove can be viewed here.

Covid-19 - The Empty Streets Of Coconut Grove

Covid-19 - The Empty Streets Of Coconut Grove

Covid-19 - The Empty Streets Of Coconut Grove

Photos of an empty South Beach can be viewed here.

Photos of an empty Downtown Miami and South Beach can be viewed here.

Photos of an empty Lincoln Road can be viewed here.

One Cocowalk Almost Completed - Set To Open Summer 2020

One Cocowalk in Coconut Grove

One Cocowalk in Coconut Grove

One Cocowalk is scheduled to open Summer 2020 as the final shape of the new 5 story Class A office building stands out on the streets of Coconut Grove.

Just over a year ago, construction reached the 3rd floor as the building started going vertical December 2018. Demolition on the old Cocowalk began May 2018 before being completed demolished September 2018.

Previous One Cocowalk Construction photos can be viewed here.

Regatta Harbour In Coconut Grove Construction Updates

Regatta Harbour Coconut Grove

Regatta Harbour Coconut Grove

Construction is well underway at the 7 acre Regatta Harbour in Coconut Grove as the Grove Bay Parking Garage is almost completed.

An Anatomy Gym will take up 14,500 square feet of space on the ground level of the parking garage that will be opened this year.

Two old Pan Am hangars have been completed stripped down and will eventually be boat storage and retail space.

After closing in November 2019, Scotty’s Landing still hasn’t been demolished, but will likely be torn down in the coming months. Next door was The Chart House restaurant that was demolished in October 2017 and will be replaced by a Cut & Dry restaurant and an Afishonado restaurant.

Construction is expected to be completed first quarter 2021.

Previous construction photos of Regatta Harbour can be viewed here.

One Park Grove Near Completion

One Park Grove

One Park Grove

One Park Grove is getting closer to completion as the finishing touches are being put on the last and final tower at Park Grove.

The landscaping around the building is almost completed while the rooftop pool should be done in the next month or so.

The 24 story tower topped off in March 2019. One Park Grove was built on the site of the old Coconut Grove Bank, which was demolished in August 2017.

Previous One Park Grove construction photos can be viewed here.