Caoba Miami Worldcenter

7th Street Apartments Reaches 21st Floor

7th Street Apartments in Downtown Miami

7th Street Apartments continues to rise in Downtown Miami and has reached the 21st floor. Previously the building was on the 13 floor at the end of May.

Construction has started on the parking garage portion of the building, but work has not started on the second tower as of yet.

Previous construction photos of 7th Street Apartments can be viewed here.

7th Street Apartments Construction Updates

7th Street Apartments

7th Street Apartments

7th Street Apartments has reached the 13th floor of the 43 story building as part of the Miami Worldcenter district. 

Previous construction photos of 7th Street Apartments can be viewed here.

7th Street Apartments Up To The 9th Floor

7th Street Apartments

7th Street Apartments

After breaking ground in June 2016, 7th Street Apartments has reached the 9th floor of the 43 story building after starting to rise in February.

The tower is expected to be completed in the Fall of 2018 and construction will begin on the second tower before the first tower is finished.

 

7th Street Apartments Starting To Rise

7th Street Apartments

The 43 story 7th Street Apartments with 450 rental units is starting to rise between NE 1st Street and North Miami Avenue. 

CIM Group purchased part of the land for $28 million, which is included in the Miami Worldcenter site. A $89 million construction loan for the site was received in December 2016.

There will also be a second rental tower with the project that will have 413 rental units. Apartments will range from studios to three bedroom units. 

Construction is expected to be completed in the fall of 2018.

Construction on Paramount Miami Worldcenter has reached the 4th floor.