TBT - Excavation Begins At Brickell Flatiron Site

Brickell Flatiron Site

Brickell Flatiron Site

TBT (September 30, 2016) - 3 years ago, foundation work was starting on the 64 story Brickell Flatiron. The building topped off in February and is expected to open soon. Construction photos of Brickell Flatiron can be viewed here.

Since groundbreaking began earlier in March, foundation work was being done at Brickell Flatiron site and now excavating has started. 

One crane has been added to the site with the base of another installed. The foundation pour is scheduled for December 2016/January 2017 with the project going vertical soon afterwards.

Previous construction photos of the Brickell Flatiron site can be viewed here.

One Cocowalk Construction Progress Photos

One Cocowalk Construction

One Cocowalk Construction

Construction is going quickly at One Cocowalk in Coconut Grove since the first glass was installed on the 5 story office building in June.

A year ago, in August 2018, the old Cocowalk was almost completed demolished and vertical construction began in December 2018.

New restaurants Sushi Garage and Botanico Gin & Cookhouse will be joining Mister O1 Extraordinary Pizza and Los Generales Mezcal & Grill as part of the revamped Cocowalk.

One Cocowalk will be open Spring 2020.

Previous photos of Cocowalk demolition and construction can be viewed here.

AMLI Residential Midtown Miami Construction Photos

AMLI Residential Midtown Miami

AMLI Residential Midtown Miami

Construction is progressing at the 6.6 acre AMLI Residential Midtown Miami project with over 700 apartment units.

A year ago, construction was starting to go vertical on the site.

Previous construction photos of the project can be viewed here.

TBT - Regatta Park Set To Open Soon

Regatta Park in Coconut Grove

Regatta Park in Coconut Grove

TBT (September 10, 2015) - 4 years ago, Regatta Park was set to open in Coconut Grove. The site was the location of the Expo Center that was demolished to make way for the park.

Regatta Park was initially supposed to be open on September 7, Labor Day, but the park is almost completed and should be ready for the public in the next few weeks. 

The three story Dockmaster building is already open and offers great views of Biscayne Bay, Downtown Miami and Coconut Grove from the top floor of the building. The old Dockmaster building, which used to be apart of Pan-Am is going to be demolished in the next week or so. The next phase for Regatta Park will be the revamp of the parking lot adjacent to the park on the East side.

Previous photos of Regatta Park can be seen here. Demolition photos of the Expo Center can be seen here at the Coconut Grove Grapevine.

Update: The Grand Opening of the park is Saturday, September 26 starting at 11am

Elysee Reaches 53rd Floor - Close To Top Off

Elysee Miami Construction

Elysee Miami Construction

The 57 story Elysee Miami is close to topping off as construction reaches the 53rd floor. At the end of July, construction was on the 45th floor.

With only 100 residential units, the building started to go vertical in June 2018, and the first glass installed in December 2018.

Developed by Two Roads Development and DW Partners, Elysee is expected to be completed in 2020.

Previous construction photos of Elysee can be viewed here.

Turnberry Ocean Club Residences Reaches 50th Floor

Turnberry Ocean Club Residences Construction

Turnberry Ocean Club Residences Construction

The Carlos Zapata designed Turnberry Ocean Club Residences in Sunny Isles Beach is 4 floors away from topping out as construction reaches the 50th floor.

Construction started going vertical on the 650 foot tower in January 2018. A year ago, construction reached the 19th floor.

Previous construction photos of the Turnberry Ocean Club Residences can be viewed here.

A Look At The Almost Completed 64 Story Brickell Flatiron

Brickell Flatiron

Brickell Flatiron

The 64 story Brickell Flatiron is getting the final touches put on the building as it nears completion.

Groundbreaking began March 2016 before topping off in February of this year. A year ago, construction was just reaching the 49th floor.

Previous construction photos of Brickell Flatiron can be viewed here.