Elysee Reaches 53rd Floor - Close To Top Off

Elysee Miami Construction

Elysee Miami Construction

The 57 story Elysee Miami is close to topping off as construction reaches the 53rd floor. At the end of July, construction was on the 45th floor.

With only 100 residential units, the building started to go vertical in June 2018, and the first glass installed in December 2018.

Developed by Two Roads Development and DW Partners, Elysee is expected to be completed in 2020.

Previous construction photos of Elysee can be viewed here.

TBT - Future Site Of Aria On The Bay

Site Of Aria on the Bay

Site Of Aria on the Bay

TBT (August 29, 2014) - Before the 53 story Aria on the Bay was built in Edgewater, a 6 story apartment complex was on the site that was eventually torn down. Demolition began on the building September 2014. Aria on the Bay was eventually completed in May 2018.

Aria on the Bay will be located in the emerging Arts & Entertainment district of Miami at 1770 North Bayshore Drive.

Developed by Melo Group and designed by Arquitectonica, Aria on the Bay will be a 53 story tower with 647 residential units. 40,000 square feet will be offered for retail, commercial and office space. The building will offer views of Biscayne Bay, Miami Beach and Margaret Pace Park is right in front. 

Currently the tenants of the previous buildings have been evacuated, but demolition has not yet started on the old apartment buildings. Homeless have been living in the evacuated apartments. 

According to exMiami, construction will not begin until February 2015 and construction is expected to be completed by 2016.

Elysee Reaches 45th Floor Of Construction

Elysee Construction

Elysee Construction

The 57 story Elysee tower in Edgewater is getting closer to topping off as construction reaches the 45th floor. In May, construction reached the 34th floor.

In June 2018, construction started going vertical on the building after the foundation pour.

Previous construction photos of Elysee can be viewed here.

Edgewater Site Sold For $13.65M

2927 NE 4th Ave

A 50,750 square foot site located at 2927 NE 4th Ave in Edgewater has sold for $13.65 million, according to The Real Deal.

The lots were purchased by DLC Capital Management and sold by AR Edgewater Investments.

The site can be zoned for 36 stories.

TBT - Biscayne Beach Construction Photos

Biscayne Beach

TBT (May 27, 2015) - Biscayne Beach was under construction in Edgewater. Biscayne Beach topped off in May 2016 and was eventually completed April 2017.

Biscayne Beach in Edgewater is starting to take form after starting construction over a year ago. 

According to The Next Miami, over 95% of the units have been sold in condo. 

The condo is located on the edge of Biscayne Bay across from the under construction Paraiso Bay from Related Group.

Elysee Reaches 34th Floor Of Construction

Elysee Construction

Elysee Construction

The 57 story Elysee in Edgewater has reached the 34th floor of construction as it gets closer to top off. Construction has reached the point in the building where it now extends further out and will extend further out once it reaches the 45th floor.

Elysee started going vertical June 2018 and should top off before the end of the year.

The parking garage also continues to get taller since it started going vertical in March.

Previous construction photos of Elysee can be viewed here.

Foundation Work Begins On Tower Portion At Missoni Baia In Edgewater

Missoni Baia Construction

Missoni Baia Construction

Foundation work is beginning on the tower portion of the 57 story Missoni Baia in Edgewater as work on the parking garage continues.

The parking garage started going vertical in September 2018 as initial work started November 2017.

Missoni Baia will eventually rise 649 feet and have 249 residential units.

The building is being developed by OKO Group, which they are also developing the under construction 830 Brickell Plaza site that will be 834 feet.