Melo Group

TBT - Future Site Of Aria On The Bay

Site Of Aria on the Bay

Site Of Aria on the Bay

TBT (August 29, 2014) - Before the 53 story Aria on the Bay was built in Edgewater, a 6 story apartment complex was on the site that was eventually torn down. Demolition began on the building September 2014. Aria on the Bay was eventually completed in May 2018.

Aria on the Bay will be located in the emerging Arts & Entertainment district of Miami at 1770 North Bayshore Drive.

Developed by Melo Group and designed by Arquitectonica, Aria on the Bay will be a 53 story tower with 647 residential units. 40,000 square feet will be offered for retail, commercial and office space. The building will offer views of Biscayne Bay, Miami Beach and Margaret Pace Park is right in front. 

Currently the tenants of the previous buildings have been evacuated, but demolition has not yet started on the old apartment buildings. Homeless have been living in the evacuated apartments. 

According to exMiami, construction will not begin until February 2015 and construction is expected to be completed by 2016.

Melo Group's Miami Plaza Reaches 11th Floor

Miami Plaza Construction

Miami Plaza Construction

The 35 story Miami Plaza in the Arts & Entertainment District is rising quickly as construction reaches the 11th floor after hitting the 6th floor last month.

The Melo Group developed project will have 425 rental units.

Previous construction photos of Miami Plaza can be viewed here.

Art Plaza Tower To Open This Month

Art Plaza

Art Plaza

The two tower Art Plaza at 34 stories in the Arts & Entertainment district is almost completed and scheduled to open this month as the final touches are being put on the building.

A year ago, construction reached the 8th floor before the East Tower topped off in November 2018 and the West Tower topping off at the beginning of this year.

Melo Group is also developing the nearby Miami Plaza, which just reached the 6th floor.

Previous construction photos of Art Plaza can be viewed here.

Miami Plaza Reaches 6th Floor Of Construction

Miami Plaza Construction

Miami Plaza Construction

The 35 story Miami Plaza in the Arts & Entertainment district has reached the 6th floor of construction.

Rising 370 feet, foundation work started in January and started going vertical in April.

Developed by Melo Group, Miami Plaza will have 425 rental units.

Cranes Installed At Miami Plaza - Starting To Go Vertical

Miami Plaza Going Vertical

Miami Plaza Going Vertical

After beginning construction in January, two cranes at Miami Plaza have been installed and construction is starting to go vertical.

The 35 story rental tower will have 425 units and rise 370 feet.

Miami Plaza is being developed by Melo Group who also have the nearby and nearly completed two tower Art Plaza.

Art Plaza Nearing Completion

Art Plaza Construction

Art Plaza Construction

The under construction Art Plaza in the Arts & Entertainment district is getting closer to completion since we last looked when the West Tower topped off in January. The East Tower topped off November 2018.

Both cranes have been removed and more of the exterior is looking like the finished product.

The East and West Tower are both 34 stories and will have a total of 667 rental units with 15,000 square feet of ground level retail.

Developed by Melo Art Plaza is next to the completion Square Station and near the under construction Miami Plaza.

Previous construction photos of Art Plaza can be viewed here.

Foundation Work Begins At Melo Group's 35 Story Miami Plaza

Foundation Work at Miami Plaza

Foundation Work at Miami Plaza

Foundation work has started at Miami Plaza located at 1502 NE Miami PL in the Arts & Entertainment District.

Developed by Melo Group, Miami Plaza will rise 35 stories at 370 feet with 425 rental units.

Melo Group also developed the nearby Square Station and the under construction Art Plaza.